"Group" Project Work

Description

This issue covers work that will be done to add "release 1" "group" (and center) functionality to Mifos X.

All types of work (i.e. requirements gathering as well as development work) are included.

The initial project approach taken is to recognize 2 streams of activity. This allows for implementation to begin with is the augmented by product management work:

1. Early Development Stream (Basic Scope)
There is no need to wait for full product management requirements/scoping output to be complete before beginning development/prototyping work. Basic scope work can start and that amounts to what 'developers' understand as being the generic group features.

2. Product Management Stream (Wider Scope)
This is scoping and requirements management.

Closing this Epic.
This issue should have a done by date and not be left always open. Once the "release version 1" scope is determined, that can be used to decide what needs to be done to resolve the Jira issue.

To Be Done: an attachment describing the documents reviewed, the Basic Scope work and has some suggestions for product management to consider.

Groups so far
=================

Groups can be created with no members. (just a name)

Environment

None
100% Done
Loading...

Activity

Show:

keithwoodlock October 23, 2012 at 9:25 AM

It just felt like the right time to close it off and as you say, when lukasz and others complete their requirements gathering process around other group functionality, they can enter/capture it any way they feel best.

Given groups is not needed for GK-maarg just thought it was right to close off this open-ended issued now.

johnwoodlock October 23, 2012 at 9:05 AM

I'm neutral on closing it. Does it help you to close it? The idea was to have a bucket that 'group' or 'Mifos' related requirements could be gathered into. i.e. the reqs gathering process that Lukasz and others are doing.

Probably Lukasz would organise it differently anyway. So, if it helps you, I'll close it now.

keithwoodlock October 23, 2012 at 8:27 AM

John, is it ok to close out the 'group' project work for now - anything futher that has to happen around groups can go in from customer focussed releases?

People can just make seperate JIRA issues (stories,improvements, etc) which we will just put into relevant release bucket

Fixed

Details

Assignee

Reporter

Components

Priority

More fields

Created August 2, 2012 at 3:11 AM
Updated October 23, 2012 at 9:25 AM
Resolved October 23, 2012 at 8:27 AM