  • Run the Datawarehouse ETL Job: You can do this manually by cd'ing into pentaho_mifosbi_1_1_windows folder and entering: 
    Panel

    initialise_datawarehouse.bat

    • For your data to be populated from Mifos into the datawarehouse, this ETL job needs to be run (typically each day just after midnight but could be less frequent if preferred). See below for instructions on scheduling the ETL job. 
Info

If you run into issues running Mifos and Pentaho simultaneously, it's because of their port numbers. Mifos by default runs on port 8080. This is where Pentaho will try to run as well. To run both applications simultaneously, you need to change the port Pentaho runs on to 8086. Follow these steps to change the port for Pentaho.

Running Mifos BI

  • Go to the biserver-ce folder in the pentaho_mifosbi_1_1_windows folder. Double-click start-pentaho.bat 

...