As a part of GSOC-16, I would be working on Mifos credit bureau integration under the guidance of Nayan Ambali and Ashok Auty.
...
5) Following additional fields would also be included in Report along with several other recommendations provided in the following report:
http://siteresources.worldbank.org/FINANCIALSECTOR/Resources/Credit_Reporting_text.pdf
Fields:
a) Number of years that the customer has been an account holder or member of the MFI
...
Time line: 3 weeks and 2 days: 26 May - 17 June
2) Highmark Equifax Integration:
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
Integration of Highmark Equifax into Mifos. This module will provide infrastructure for request/response to and from highmarkEquifax
Timeline: 2 weeks: 20 June - 1 July
...