Feature | Task | Resource | Planned start date | Planned completion date | Actual completion date | Overall Status | Comment | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Tally Accounting Integration |
|
|
|
| |
| |||||||||||||||
| Document Test Plan and Cases | Jeff | 1-Sept-10 | 7-Sep-10 | not on wiki! |
|
| ||||||||||||||
| Execute manual tests | Jeff | 3-Sept-10 | 10-Sept-10 | 14-Sep-10 |
|
| ||||||||||||||
| Develop automated acceptance tests | Jeff | need spike first |
|
|
|
| ||||||||||||||
Waive Interest on Loan Repayment |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Deepak | 2-Nov-10 | 4-Nov-10 |
|
| |||||||||||||||
| Execute manual tests | Deepak | 3-Nov-10 | 4-Nov-10 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Deepak | May have already |
|
|
|
| ||||||||||||||
Quartz Batch Jobs |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Lukasz | 8-Nov-2010 | 9-Nov-2010 |
|
| |||||||||||||||
| Execute manual tests | Lukasz | 10-Nov-2010 | 12-Nov-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Lukasz | 10-Nov-2010 | 12-Nov-2010 |
|
|
| ||||||||||||||
PPI |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Jeff | 8-Nov-2010 | 9-Nov-2010 |
|
| |||||||||||||||
| Execute manual tests | Jeff | 10-Nov-2010 | 16-Nov-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Jeff | 16-Nov-2010 | 23-Nov-2010 |
|
|
| ||||||||||||||
Question Groups |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Tejus/Lukasz | 20-Oct-2010 | 26-Oct-2010 |
|
| |||||||||||||||
| Execute manual tests | Tejus/Lukasz | 25-Oct-2010 | 12-Nov-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Tejus/Lukasz | 8-Nov-2010 | 17-Nov-2010 |
|
|
| ||||||||||||||
Data Migration of Surveys and Add. Fields |
|
|
|
|
|
|
| ||||||||||||||
| Document Test Plan and Cases | Tejus/Lukasz | 15-Nov-2010 | 16-Nov-2010 |
|
|
| ||||||||||||||
| Execute manual tests | Tejus/Lukasz | 17-Nov-2010 | 19-Nov-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Tejus/Lukasz | 22-Nov-2010 | 24-Nov-2010 |
|
|
| ||||||||||||||
MPESA |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Jeff/Lukasz | 25-Oct-2010 | 26-Oct-2010 |
|
| |||||||||||||||
| Execute manual tests | Jeff/Lukasz | 27-Oct-2010 | 29-Oct-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Jeff/Lukasz | 25-Oct-2010 | 29-Oct-2010 |
|
|
| ||||||||||||||
Savings Interest |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Kojo | 20-Oct-2010 | 22-Oct-2010 |
|
| |||||||||||||||
| Execute manual tests | Kojo | 02-Nov-2010 | 04-Nov-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Kojo | 05-Nov-2010 | 15-Nov-2010 |
|
|
| ||||||||||||||
Freemarker |
|
|
|
|
|
| |||||||||||||||
| Document Test Plan and Cases | Lukasz | 21-Oct-2010 | 22-Oct-2010 |
|
| |||||||||||||||
| Execute manual tests | Lukasz | 25-Oct-2010 | 29-Oct-2010 |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Lukasz | 01-Nov-2010 | 05-Nov-2010 |
|
|
| New Leila E Reports |
|
|
|
|
|
|
| Document Test Plan and Cases | Gray Matter | 27-Oct-2010 | 3-Nov-2010 |
|
|
| Execute manual tests | Gray Matter | tbd | tbd |
|
|
| ||||||||||||||
| Develop automated acceptance tests | Gray Matter | tbd | tbd |
|
|
| ||||||||||||||
|
|
|
|
|
|
|
| ||||||||||||||
| Performance tests (in parallel with functional testing) | Sungard | continiously | 15-Nov-2010 |
|
| |||||||||||||||
|
|
|
|
|
|
|
| ||||||||||||||
| Upgrade tests | Jeff | 1-Dec-2010 | 3-Dec-2010 |
|
|
| ||||||||||||||
|
|
|
|
|
|
|
| ||||||||||||||
| Leila E features functional testing complete |
| n/a | 26-Nov-2010 |
|
|
| ||||||||||||||
| Regression testing | All | 30-Nov-2010 | 15-Dec-2010 |
|
|
| ||||||||||||||
| Bug Verification Complete | All | n/a | 15-Dec-2010 |
|
|
| ||||||||||||||
|
|
|
|
|
|
|
| ||||||||||||||
| Final Candidate Acceptance and Regression Testing | All | 16-Dec-2010 | 20-Dec-2010 |
|
|
| ||||||||||||||
|
|
|
|
|
|
|
| ||||||||||||||
| Test Release Candidate |
| 21-Dec-2010 | 21-Dec-2010 |
|
|
| ||||||||||||||
| Release |
| n/a | 22-Dec-2010 |
|
|
| ||||||||||||||
| Test Report |
| 22-Dec-2010 | 24-Dec-2010 |
|
|
|
Page Comparison
Manage space
Manage content