Feature | Task | Resource | Planned start date | Planned completion date | Actual completion date | Overall Status | Comment |
---|---|---|---|---|---|---|---|
Tally Accounting Integration |
|
|
|
| |
| |
| Document Test Plan and Cases | Jeff | 1-Sept-10 | 7-Sep-10 | not on wiki! |
|
|
| Execute manual tests | Jeff | 3-Sept-10 | 10-Sept-10 | 14-Sep-10 |
|
|
| Develop automated acceptance tests | Jeff | need spike first |
|
|
|
|
Waive Interest on Loan Repayment |
|
|
|
|
|
| |
| Document Test Plan and Cases | Deepak | 2-Nov-10 | 4-Nov-10 |
|
| |
| Execute manual tests | Deepak | 3-Nov-10 | 4-Nov-10 |
|
|
|
| Develop automated acceptance tests | Deepak | May have already |
|
|
|
|
Quartz Batch Jobs |
|
|
|
|
|
| |
| Document Test Plan and Cases | Wojciech | 8-Nov-2010 | 9-Nov-2010 |
|
| |
| Execute manual tests | Wojciech | 10-Nov-2010 | 12-Nov-2010 |
|
|
|
| Develop automated acceptance tests | Wojciech | 10-Nov-2010 | 12-Nov-2010 |
|
|
|
PPI |
|
|
|
|
|
| |
| Document Test Plan and Cases | Jeff | 8-Nov-2010 | 9-Nov-2010 |
|
| |
| Execute manual tests | Jeff | 10-Nov-2010 | 16-Nov-2010 |
|
|
|
| Develop automated acceptance tests | Jeff | 16-Nov-2010 | 23-Nov-2010 |
|
|
|
Question Groups |
|
|
|
|
|
| |
| Document Test Plan and Cases | Tejus/Lukasz | 20-Oct-2010 | 26-Oct-2010 | 27-Oct-2010 |
|
|
| Execute manual tests | Wojciech | 25-Oct-2010 | 12-Nov-2010 |
|
|
|
| Develop automated acceptance tests | Wojciech | 8-Nov-2010 | 17-Nov-2010 |
|
|
|
Data Migration of Surveys and Add. Fields |
|
|
|
|
|
|
|
| Document Test Plan and Cases | Wojciech/Jeff | 15-Nov-2010 | 16-Nov-2010 |
|
|
|
| Execute manual tests | Wojciech/Jeff | 17-Nov-2010 | 19-Nov-2010 |
|
|
|
| Develop automated acceptance tests | Wojciech/Jeff | 22-Nov-2010 | 24-Nov-2010 |
|
|
|
MPESA |
|
|
|
|
|
| |
| Document Test Plan and Cases | Jeff/Lukasz | 25-Oct-2010 | 26-Oct-2010 | 26-Oct-2010 |
|
|
| Execute manual tests | Jeff/Lukasz | 27-Oct-2010 | 29-Oct-2010 | 29-Oct-2010 - but need to update MIFOSTEST project cases |
|
|
| Develop automated acceptance tests | Jeff/Lukasz | 25-Oct-2010 | 3-Nov-2010 | one in test in place - need more cases |
|
|
Savings Interest |
|
|
|
|
|
| |
| Document Test Plan and Cases | Kojo | 20-Oct-2010 | 22-Oct-2010 |
|
| |
| Execute manual tests | Kojo | 02-Nov-2010 | 04-Nov-2010 |
|
|
|
| Develop automated acceptance tests | Kojo | 05-Nov-2010 | 15-Nov-2010 |
|
|
|
Freemarker |
|
|
|
|
|
| |
| Document Test Plan and Cases | Lukasz | 21-Oct-2010 | 22-Oct-2010 | 22-Oct-2010 |
|
|
| Execute manual tests | Lukasz | 25-Oct-2010 | 29-Oct-2010 | 29-Oct-2010 - some bug fix verifications to complete |
|
|
| Develop automated acceptance tests | Wojciech | 01-Nov-2010 | 05-Nov-2010 |
|
|
|
...
|
|
|
|
|
|
|
|
| Performance tests (in parallel with functional testing) | Sungard | continuously | 15-Nov-2010 |
|
| |
|
|
|
|
|
|
|
|
| Upgrade tests | Jeff | 1-Dec-2010 | 3-Dec-2010 |
|
|
|
|
|
|
|
|
|
|
|
| Leila E features functional testing complete |
| n/a | 26-Nov-2010 |
|
|
|
| Regression testing | All | 30-Nov-2010 | 15-Dec-2010 |
|
|
|
| Bug Verification Complete | All | n/a | 15-Dec-2010 |
|
|
|
|
|
|
|
|
|
|
|
| Final Candidate Acceptance and Regression Testing | All | 16-Dec-2010 | 20-Dec-2010 |
|
|
|
|
|
|
|
|
|
|
|
| Test Release Candidate |
| 21-Dec-2010 | 21-Dec-2010 |
|
|
|
| Release |
| n/a | 22-Dec-2010 |
|
|
|
| Test Report |
| 22-Dec-2010 | 24-Dec-2010 |
|
|
|