4. Front End development to view user data
5. testing/documentation
Schedule/Timeline
Schedule upto mid term evaluation
Week # | Task | Description | Expected due date |
---|---|---|---|
1 19.05.2014 to 26.05.2014 |
| After completing this task Run reports API will capable of generating reports regarding total number of clients that have at least one outstanding loan and/or an open position | 26.05.2014 |
2 26.05.2014 to 02.06.2014 | Writing SQL to generate voluntary Savings amount and Compulsory Savings amount and adding API | Run report API will be capable of creating reports for savings to get sum of the balances of all voluntary and compulsory savings after completing this task. | 02.06.2014 |
3 02.06.2014 to 09.06.2014 | Writing SQL to generate loan related reports listed above and adding to API | Run reports will be generated related to outstanding loans( number and principal), PAR 1% and PAR 30% | 09.06.2014 |
4 09.06.2014 to 16.06.2014 |
| Completing of previous weeks tasks and adding API documentation, DB caching to improve performance | 16.06.2014 |
5 16.06.2014 to 23.06.2014 | Finalizing all the back end run report API tasks and API documentation | By this week all the back end support for Client Impact Portal will be delivered | 23.06.2014 |