Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

two workbooks
TimelineObjectives
Week 1 (June 09) Implementing the workflow with a simple entity such as Office.
Week 2 (June July 16)
  • Implementing Client Import template where the first sheettwo sheets of workbook is are pre-formatted with existing Offices  entered through the MifosX platform and these constraints are imposed on the second worksheet.Implement  Personnel Details import template where the first sheet of workbook is pre-formatted with existing Offices entered through the Mifosx MifosX platform and these constraints are imposed on the second third worksheet.
  • Import of the above two workbooksworkbook.
Week 3 (June July 23)
  • Implementing Client Loan import template where the first three sheets of workbook is pre-formatted with existing Loan Product configuration  and Loan Officers configuration entered through the MifosX platform and Clients and Loan Officers entered in the above step and these constraints are imposed on the fourth worksheet
  • Import of the above workbook
Week 4 (July 30)
  • Continue on the above task.
Week 5 (Aug 6)
  • Implementing Client Repayment History import template where the first sheet of workbook is pre-formatted with Client Loans imported in the first step and these constraints are imposed on the second worksheet.
  • Import of the above
  • workbook.
Week 6 (Aug 13)
  • Check the workflow through various test cases if the code breaks anywhere
Week 4 7 (June 29Aug 20)
  • Implement Saving Account import template where the first two sheets of workbook is pre-formatted with existing Offices and Clients imported in the first step and these constraints are imposed on the third worksheet. 
  • Import the above workbook.
Week 5 (Aug 4)Mid-term evaluations
Week 6 (Aug 11)TBD
Week 7 (Aug 18)TBD
Week 8 (Aug 2527)TBD
  • Implement Savings Transactions import template and importing the workbook.
Week 9 (Sept 1)Implement any validation code that is missing in the platform regarding data import3)
  • Implement Groups import template (including Meetings import) and importing the workbook.
Week 10 (Sept 810)Refactor the code base.
Week 11 (Sept 15)Check through various test cases if the code breaks anywhere. 
Week 12 (Sept 27)Write tests, documentation, and submit final evaluation.

...

  •  Integrating support for groups in Group Lending and Group Savings.

 

Week 11 (Sept 22)
  • Write unit tests and document the work.

Project Details

JIRA: https://mifosforge.jira.com/browse/MIFOSX-120

Github: https://github.com/avarice010openMF/DataImportDataImportTool