Page Properties
Target release
Epic
Source Code
Project Status
Status
titlePre-Planning
WORK IN PROGRESS
Document status
Status
titleDRAFT
Document ownerChannaS
DesignerSander van der Heyden
DevelopersChannaS
QA

Project Summary

Goals

    • Implement back-end logic in MifosX required to make information available to the client impact portal
    • Implement UI and back-end logic of the Client impact portal

Background, Impact, and User Need

Microfinance institutions usually work with various external parties, such as funders or investors. Using the data that is available in MifosX we would like to offer those stakeholders a seperate portal showing accurate and high-level information about the institution that would otherwise be reported manually by the institution. This information helps them in their decision making processes, but also enables them to assess the broader impact they are having with their funding.

...

LoansDescription
Outstanding Loans (principal)Outstanding principal of all outstanding loans of the institution
Outstanding Loans (number)

Total number of all outstanding loans of the institution

PAR 1 (%)The outstanding principal of all outstanding loans of the institution that have at least one payment >1 day in arrears divided by the Outstanding Loans and shown as a %
PAR 30 (%)The outstanding principal of all outstanding loans of the institution that have at least one payment >30 day in arrears divided by the Outstanding Loans and shown as a %
SavingsDefinition
Voluntary Savings (amount)Sum of the balances of all voluntary savings accounts in the institution
Compulsory Savings (amount)Sum of the balances of all compulsory savings accounts in the institution
ClientsDefinition
Total number of clientsThe total number of clients that have at least one outstanding loan and/or an open position (savings, deposits)

Deliverables

  1. Back end API code for impact portal (source code with comments and test cases)
    1. Generating the datapoints listed above for clients, loans, savings
        Ma
        1. Writing the SQLs
        2. Adding the APIs
      1. Datapoints generated and cached in the DB for performance
    2. Update API documentation and wiki page

        ...

          1. How to use this new API endpoint for retrieving data
          2. How to extend the number of datapoints
        1. Impact Portal Front end (Source code)
        2. User manual/ Documentation 

        Project Implementation Plan

        1. Creating Impact Portal Front end

        ...


           4. Front End development to view user data
           5. testing/documentation

         

         

         

        Schedule/Timeline

        Schedule upto mid term evaluation

        Week #TaskDescriptionExpected due date

        1

        19.05.2014 to 26.05.2014

        • Writing SQL to retrieve total number of clients
        • Adding API 
        After completing this task Run reports API will capable of generating reports regarding total number of clients  that have at least one outstanding loan and/or an open position26.05.2014

        2

        26.05.2014 to 02.06.2014

        Writing SQL to generate voluntary Savings amount and Compulsory Savings amount and adding APIRun report API will be capable of creating reports for savings to get sum of the balances of all voluntary and compulsory savings after completing this task.02.06.2014

        3

        02.06.2014 to 09.06.2014

        Writing SQL to generate loan related reports listed above and adding to API Run reports will be generated related to outstanding loans( number and principal), PAR 1% and PAR 30%09.06.2014

        4

        09.06.2014 to 16.06.2014

        • Datapoints creation and adding DB cache to improve performance.
        • API documentation and wiki page update regarding using/extending of new API endpoints

         

        Completing of previous weeks tasks and adding API documentation, DB caching to improve performance16.06.2014

        5

        16.06.2014 to 23.06.2014

        Finalizing all the back end run report API tasks and API documentationBy this week all the back end support for Client Impact Portal will be delivered 23.06.2014

         

        Schedule from mid term to final evaluation. 

        WeekTaskDescriptionExpected Due Date

        30.06.2014 to

        07.07.2014

        Adding basic view components to home page

        (for no of clients, loans, savings etc)

        graphs, pie charts and other suitable components07.07.2014

        07.07.2014 to

        14.07.2014

        adding database to store users and related tenants

        with those users.

        users with associated tenants.14.07.2014

        14.07.2014 to

        28.07.2014

        adding user sign in/out with backend api callbasic authentication with backend.28.07.2014

        28.07.2014 to

        04.07.2014

        adding backend data to portal components.(created datapoints

        will be used to retrieve data)

        backend front end connectivity for components in the front end04.07.2014

        04.07.2014 to

        11.07.2014

        Documentation fine tuning and adding necessary changes. 11.07.2014

         

        Additional Resources

        Requirements

        Assumptions

        User Stories

        #TitleUser StoryImportanceNotes
        1
             

        User interaction and design

        Questions

        Below is a list of questions to be addressed as a result of this requirements document:

        QuestionOutcome

        Not Doing

        •