Tally Accounting Integration |
|
|
|
|
|
|
|
|
Document Test Plan and Cases |
Jeff |
1-Sept-10 |
7-Sep-10 |
not on wiki! |
|
|
|
Execute manual tests |
Jeff |
3-Sept-10 |
10-Sept-10 |
14-Sep-10 |
|
|
|
Develop automated acceptance tests |
Jeff |
need spike first |
|
|
|
|
Waive Interest on Loan Repayment |
|
|
|
|
|
- issue MIFOS-4040 |
|
|
Document Test Plan and Cases |
Deepak |
2-Nov-10 |
4-Nov-10 |
|
|
|
|
Execute manual tests |
Deepak |
3-Nov-10 |
4-Nov-10 |
|
|
|
|
Develop automated acceptance tests |
Deepak |
May have already |
|
|
|
|
Quartz Batch Jobs |
|
|
|
|
|
- has been checked in and working for some time. Udai investigating errors on test server with batch jobs. Test pass scheduled for mid November |
|
|
Document Test Plan and Cases |
Wojciech |
8-Nov-2010 |
9-Nov-2010 |
|
|
|
|
Execute manual tests |
Wojciech |
10-Nov-2010 |
12-Nov-2010 |
|
|
|
|
Develop automated acceptance tests |
Wojciech |
10-Nov-2010 |
12-Nov-2010 |
|
|
|
PPI |
|
|
|
|
|
|
|
|
Document Test Plan and Cases |
Jeff |
8-Nov-2010 |
9-Nov-2010 |
|
|
|
|
Execute manual tests |
Jeff |
10-Nov-2010 |
16-Nov-2010 |
|
|
|
|
Develop automated acceptance tests |
Jeff |
16-Nov-2010 |
23-Nov-2010 |
|
|
|
Question Groups |
|
|
|
|
|
- ENDA report issues must be fixed |
|
|
Document Test Plan and Cases |
Tejus/Lukasz |
20-Oct-2010 |
26-Oct-2010 |
27-Oct-2010 |
|
|
|
Execute manual tests |
Wojciech |
25-Oct-2010 |
12-Nov-2010 |
|
|
|
|
Develop automated acceptance tests |
Wojciech |
8-Nov-2010 |
17-Nov-2010 |
|
|
|
Data Migration of Surveys and Add. Fields |
|
|
|
|
|
- need customer data migrations. Upgrade performance blocked by MIFOS-4043 |
|
|
Document Test Plan and Cases |
Wojciech/Jeff |
15-Nov-2010 |
16-Nov-2010 |
|
|
|
|
Execute manual tests |
Wojciech/Jeff |
17-Nov-2010 |
19-Nov-2010 |
|
|
|
|
Develop automated acceptance tests |
Wojciech/Jeff |
22-Nov-2010 |
24-Nov-2010 |
|
|
|
MPESA |
|
|
|
|
|
- Jakub needs to review automated tests, manual test cases need to be updated |
|
|
Document Test Plan and Cases |
Jeff/Lukasz |
25-Oct-2010 |
26-Oct-2010 |
26-Oct-2010 |
|
|
|
Execute manual tests |
Jeff/Lukasz |
27-Oct-2010 |
29-Oct-2010 |
29-Oct-2010 - but need to update MIFOSTEST project cases |
|
|
|
Develop automated acceptance tests |
Jeff/Lukasz |
25-Oct-2010 |
3-Nov-2010 |
one in test in place - need more cases per Jakub |
|
|
Savings Interest |
|
|
|
|
|
- Kojo pairing with Keith and Udai on current test coverage, required acceptance level tests |
|
|
Document Test Plan and Cases |
Kojo |
20-Oct-2010 |
22-Oct-2010 |
Kojo - need new dates! |
|
|
|
Execute manual tests |
Kojo |
02-Nov-2010 |
04-Nov-2010 |
|
|
|
|
Develop automated acceptance tests |
Kojo |
05-Nov-2010 |
15-Nov-2010 |
|
|
|
Freemarker |
|
|
|
|
|
- still some open ftl bugs |
|
|
Document Test Plan and Cases |
Lukasz |
21-Oct-2010 |
22-Oct-2010 |
22-Oct-2010 |
|
|
|
Execute manual tests |
Lukasz |
25-Oct-2010 |
29-Oct-2010 |
29-Oct-2010 - some bug fix verifications to complete |
|
|
|
Develop automated acceptance tests |
Wojciech |
01-Nov-2010 |
05-Nov-2010 |
|
|
|
|
|
|
|
|
|
|
|
GENERAL TASKS>> |
---------------------- |
--------- |
------------- |
------------- |
---------------- |
---------------------- |
|
|
Performance tests (in parallel with functional testing) |
Sungard |
continuously |
15-Nov-2010 |
|
|
|
|
|
|
|
|
|
|
|
|
Upgrade tests |
Jeff |
1-Dec-2010 |
3-Dec-2010 |
|
|
|
|
|
|
|
|
|
|
|
|
Leila E features functional testing complete |
|
n/a |
26-Nov-2010 |
|
|
|
|
Regression testing |
All |
30-Nov-2010 |
15-Dec-2010 |
|
|
|
|
Bug Verification Complete |
All |
n/a |
15-Dec-2010 |
|
|
|
|
|
|
|
|
|
|
|
|
Final Candidate Acceptance and Regression Testing |
All |
16-Dec-2010 |
20-Dec-2010 |
|
|
|
|
|
|
|
|
|
|
|
|
Test Release Candidate |
|
21-Dec-2010 |
21-Dec-2010 |
|
|
|
|
Release |
|
n/a |
22-Dec-2010 |
|
|
|
|
Test Report |
|
22-Dec-2010 |