- What did you accomplish this past week?
- Now ui library has enough styles and attributes to be usable with both the mifos-mobile and mobile-wallet. Some parts are still pending.
- Make use of ui library with mifos-mobile app
- What will you do this upcoming week?
- Make ui-library fully usable mifos-mobile and mobile-wallet
- Add some additional styles and attributes
- Have android client start using UI library
- Extract other common components in future - cards, list items, data tables and many other attributes that need to be shown - refactor to use UI library
- What obstacles are impeding your progress?
- Data tables for mobile wallet are not there
- Demo credentials not working
- https://mifos.mobile.io
- Would you like help from some mentor for this task?
- Action: ed to continue getting feedback from mentors on his PRs - screenshots, recordings of apps now in the PRs.
- Action; Ed to get stable demo infrastru ture in place to ping Victor.
Prashant Singh
- What did you accomplish this past week?
- What will you do this upcoming week?
- What obstacles are impeding your progress?
- Would you like help from some mentor for this task?
...
- What did you accomplish this past week?
- FInished Collateral Module feature completely which cover -
- Create, Edit, Delete client level Collateral
- Added functionality to add the collateral to the loans,
- Added the custom validators which check is the collaterals being added are valid and has value more than the loan principal.
- Fixed the 1440 and 1471 issue
- Started work on new feature GLIM interface.
- FInished Collateral Module feature completely which cover -
- What will you do this upcoming week?
- WIll work on GLIM and GSIM interface. which include
- Create functionality, Overview and View component
- Will Start work on Collection Sheets new feature or internationalization.
- WIll work on GLIM and GSIM interface. which include
- What obstacles are impeding your progress?
- Nothing.
- API failing in collection sheet even in community app
- Issue has been raised in Fineract that it's failing. After complete GLIM and GSIM interface this will be.a blocker.
- Would you like help from some mentor for this task?
- No.
- Action: ed to follow up with Aleks and Karan and Alberto around moving forward with i18n, testing, and typescript client usage.
Anmol Gupta
- What did you accomplish this past week?
- What will you do this upcoming week?
- What obstacles are impeding your progress?
- Would you like help from some mentor for this task?
...
- What did you accomplish this past week?
- Add the predict function to the FL model and now we finish the server and client code
- Integrage Integrate the functions together and test the code
- Add some errors handling functions
- What will you do this upcoming week?
- We will begin to integrate them into the Django restful framework
- Need to adjust the basic neural network model structure
- Think about how to deal with the situation that multiple clients connected together
- What obstacles are impeding your progress?
- Would you like help from some mentor for this task?
- Action: Ed to reach out to Lalit and Jeremy to join demo/showcase session.
Suchith Donni
- What did you accomplish this past week?
- Studied various encryption techniques and its implementation
- Started working on H2O.ai to make the models more robust across distributed networks
- Got ready for the showcase scheduled this week.
- What will you do this upcoming week?
- Integration and deployment
- Work towards scalability and data collection
- What obstacles are impeding your progress?
- None
- Would you like help from some mentor for this task?
- None
...