Before Release
TeVMH Team | Indiv Owner | Task | Due Date | Status | ||
---|---|---|---|---|---|---|
Eng | KC | Communicate code freeze on release | 4/21 | done | ||
Eng | ALL | Code Freeze | 4/22 | done | ||
Eng | VMH | Set revision numbers for reports, update version numbers of all reports changed since 1.1 to 1.2, and also make sure all new reports have 1.2 version on them | 4/25 | done | ||
Eng | VMH | Create release branch | 4/25 | done | ||
Eng | SS/VMH | Auto-build of release branch on continuous integration server and creates artifact | 4/25 | done | ||
All | KC | Scrub bug list during general bug triage meeting; fixing only show-stoppers after this point | 4/25 | done | ||
PM | EC | Communicate release schedule to community and on mifos.org roadmap | 4/25 |
| -- | |
QA | LC | Complete functional testing, iSS/VMHue issue verification on 1.2 reports | 4/25 | done | ||
Eng | VMH | Double-check licenses of any 3rd party libraries added since last release - none | 4/25 | done | ||
Eng | SS/VMH | Update any changes to Pentaho configuration | 4/25 |
| -- | |
Eng | SS VMH/VMH JW | Update Developer / Sys Admin Documentation - including Install ProceSS/VMHProcess, Upgrade ProceSS/VMH | 4/26 | Process |
| in progress |
Eng | KC | Update Release Notes, Upgrade Notes if any | 4/26 | done | ||
Eng | VMH | Final Release Candidate build ready - no changes allowed after this date | 4/26 | done | ||
PM | KC | Update Functional Specs | 4/26 | done | ||
Eng | VMH | Identify final release candidate (binary release Zip File with reports, etc). | 4/26 | done | ||
QA | LC | Testing of Release Candidate Complete, give go-ahead (do diff w/ previous release) | 4/26 | done | ||
Biz | EC | Create Draft announcement, download page for mifos.org | 4/27 |
| ||
PM/Eng | KC | Create Draft announcement for community | 4/27 |
| ||
PM/Eng | VMH/KC | Final Documentation ready (release notes, install doc, etc) | 4/27 |
| ||
Eng | VMH | Test Download, release notes pre-release page | 4/27 |
| ||
Eng |
| Release Day: see below | 4/27 |
|
Release Day
TeVMH Owner | Indiv Owner | Task | Status |
---|---|---|---|
Eng | VMH | Upload Release Binary Zip |
|
QA | LC | Test Live Download |
|
All | EC | Announce Release on mifos.org |
|
PM/Eng | KC | Announce Release on developer and user lists |
|
PM/Eng | KC | Announce Release on Sourceforge |
|
Biz |
| Announce Release internally at GF |
|
...