Automated Regression Testing
Business Goals
- Reduce manual test execution at end of Mifos release cycle from 3 weeks to 1 week by automating backlog of manual test cases.
- Correct and simplify existing automated tests
- Speed up creation and maintenance of acceptance tests
Project Staff
Role |
Team Member |
---|---|
GF Technical Lead |
Jeff Brewster |
Project Lead |
Lukasz Chudy |
Project Engineer |
Łukasz Domżalski |
Project Engineer |
Paweł Fryca |
Project Engineer |
Patryk Dereszewski |
Project Engineer |
Marcin Modrzejewski |
Project Deliverable and Status
Deliverable |
Status |
---|---|
Documented Assessment of existing automated acceptance tests and corresponding test cases |
Done, attached |
Corrections to existing automated acceptance tests |
|
Automated tests committed on head-master for test cases that are flagged as "manual" |
see weekly progress below |
Project Time-line
Start date: January 10, 2011
Estimated end date: March 10, 2011
Weekly progress towards project completion
This data is pulled from the Mifos test case dashboard. We will track the number of test cases that are automated per week.
Date |
Number of automated tests cases |
Number of manual test cases to be automated |
Number of automated tests running on birch |
---|---|---|---|
10-Jan-2011 |
115 |
240 |
203 |
17-Jan-2011 (test case reduction) |
78 |
231 |
203 |
24-Jan-2011(more test case reduction) |
64 |
125 |
198 |
25-Jan-2011 (test cases reduction finished) |
31 |
139 |
199 |
31-Jan-2011 |
46 |
123 |
209 (13 added, 3 deleted) |
7-Feb-2011 |
77 |
91 |
241 |
14-Feb-2011 |
94 |
74 |
255 |
21-Feb-2011 |
129 |
46 |
271 |
28-Feb-2011 |
162 |
8 |
249 |
07-Mar-2011 |
182 |
0 |
284 |