Automated Regression Testing

Business Goals

  1.  Reduce manual test execution at end of Mifos release cycle from 3 weeks to 1 week by automating backlog of manual test cases.
  2.  Correct and simplify existing automated tests
  3.  Speed up creation and maintenance of acceptance tests

Project Staff

Role

Team Member

GF Technical Lead

Jeff Brewster

Project Lead

Lukasz Chudy

Project Engineer

Łukasz Domżalski

Project Engineer

Paweł Fryca

Project Engineer

Patryk Dereszewski

Project Engineer

Marcin Modrzejewski

Project Deliverable and Status

Deliverable

Status

Documented Assessment of existing automated acceptance tests and corresponding test cases

Done, attached

Corrections to existing automated acceptance tests

 

Automated tests committed on head-master for test cases that are flagged as "manual"

see weekly progress below

Project Time-line

Start date: January 10, 2011
Estimated end date: March 10, 2011

Weekly progress towards project completion

This data is pulled from the Mifos test case dashboard. We will track the number of test cases that are automated per week.

Date

Number of automated tests cases

Number of manual test cases to be automated

Number of automated tests running on birch

10-Jan-2011

115

240

203

17-Jan-2011 (test case reduction)

78

231

203

24-Jan-2011(more test case reduction)

64

125

198

25-Jan-2011 (test cases reduction finished)

31

139

199

31-Jan-2011

46

123

209  (13 added, 3 deleted)

7-Feb-2011

77

91

241

14-Feb-2011

94

74

255

21-Feb-2011

129

46

271

28-Feb-2011

162

8

249

07-Mar-2011

182

0

284