Testing Schedule - Leila E

Feature

Task

Resource

Planned start date

Planned completion date

Actual completion date

Overall Status

  1. (plus) =  no serious bugs
  2. (warning)  = issues to be fixed for this release
  3. (error)  = blocked by serious bugs,
  4. (question) = no status yet
    status as of 9 November 2010

Comment

Tally Accounting Integration


 

 

 

 

(plus)

 

 

Document Test Plan and Cases

Jeff

1-Sept-10

7-Sep-10


 

 

 

Execute manual tests

Jeff 

3-Sept-10

10-Sept-10

14-Sep-10

 

 

 

Develop automated acceptance tests

Jeff 

need spike first

 

 

 

 

Waive Interest on Loan Repayment


 

 

 

 

      (plus)

 

 

Document Test Plan and Cases

Deepak

2-Nov-10

4-Nov-10

9-Nov-10

test cases in Jira 709, 710, 711

 

 

 

 

 

Execute manual tests

Deepak

3-Nov-10

4-Nov-10

9-Nov-10

 

 

 

Develop automated acceptance tests

Deepak

May have already
completed-need to check

 

 

One end to end automated test in place.
org.mifos.test.acceptance.loan.WaiveLoanFeeTest

 

Quartz Batch Jobs


 

 

 

 

(plus)

 

 

Document Test Plan and Cases

Wojciech

8-Nov-2010

9-Nov-2010

9-Nov-10

summarized test cases for Quartz, see Testing Plans page.

 

 

Execute manual tests

Wojciech

10-Nov-2010

12-Nov-2010

9-Nov-10


 

 

Develop automated acceptance tests

Wojciech

10-Nov-2010

12-Nov-2010

9-Nov-10

6 automated test cases are in place

 

PPI


 

 

 

 

(plus)

 

 

Document Test Plan and Cases

Jeff

8-Nov-2010

9-Nov-2010

12-Nov-10

 

 

 

Execute manual tests

Jeff

10-Nov-2010

19-Nov-2010

 

 

 

 

Develop automated acceptance tests

Jeff

12-Nov-2010

23-Nov-2010

 

 

 

Question Groups


 

 

 

 

(plus)

 

 

Document Test Plan and Cases

Tejus/Lukasz

20-Oct-2010

26-Oct-2010

27-Oct-2010


 

 

Execute manual tests

Wojciech

25-Oct-2010

12-Nov-2010

 

Doing retest on verifications, Deepak may also do more testing on question groups.  Some manual tests are still needing to be automated.

 

 

Develop automated acceptance tests

Wojciech

8-Nov-2010

17-Nov-2010

 

org.mifos.test.acceptance.questionnaire.QuestionTest

 

Data Migration of Surveys and Add. Fields

 

 

 

 

 

(plus)

 

 

Document Test Plan and Cases

Wojciech/Jeff

15-Nov-2010

16-Nov-2010

 

 

 

 

Execute manual tests

Wojciech/Jeff

17-Nov-2010

19-Nov-2010

 

 

 

 

Develop automated acceptance tests

Wojciech/Jeff

22-Nov-2010

24-Nov-2010

 

 

 

MPESA


 

 

 

 

(plus) - Manual test progress has been updated. I have checked that the current acceptance test is quite sophisticated and covers a lot of cases. The question is if we need all test cases (with all steps) to be automated, or if the current test is sufficient for us.

 

 

Document Test Plan and Cases

Jeff/Lukasz

25-Oct-2010

26-Oct-2010

26-Oct-2010


 

 

Execute manual tests

Jeff/Lukasz

27-Oct-2010

29-Oct-2010

29-Oct-2010

 

 

 

Develop automated acceptance tests

Jeff/Lukasz

25-Oct-2010

3-Nov-2010

27-Oct-2010 (MpesaImportTest)

 

 

Savings Interest


 

 

 

 

(plus)  - Executing manual tests

 

 

Document Test Plan and Cases

Kojo

05-Nov-2010

09-Nov-2010

26-Nov-2010

 

 

 

Execute manual tests

Kojo

04-Nov-2010

10-Dec-2010

 

 

 

 

Develop automated acceptance tests

Kojo

 

 

 

The effort will rather be spent on spiking functional tests at the API level for savings.

 

Freemarker


 

 

 

 

(plus)

 

 

Document Test Plan and Cases

Lukasz

21-Oct-2010

22-Oct-2010

22-Oct-2010


 

 

Execute manual tests

Lukasz

25-Oct-2010

29-Oct-2010

29-Oct-2010


 

 

Develop automated acceptance tests

Wojciech

01-Nov-2010

05-Nov-2010

 

some current cases can be automated to cover new ftl pages.

 

 

 

 

 

 

 

 

 

GENERAL TASKS>>

----------------------

---------

-------------

-------------

----------------

----------------------

 

 

Performance tests (in parallel with functional testing)

Sungard

continuously

15-Nov-2010


(plus)

 

 

 

 

 

 

 

 

 

 

Upgrade tests

Jeff

1-Dec-2010

3-Dec-2010

 

(plus) - (see migration)

 

 

 

 

 

 

 

 

 

 

Leila E features functional testing complete

 

n/a

26-Nov-2010

done

(plus)

 

 

Regression testing

All

30-Nov-2010

15-Dec-2010

 

(plus)

 

 

Bug Verification Complete

All

n/a

15-Dec-2010

 

(plus)

 

 

 

 

 

 

 

 

 

 

Final Candidate Acceptance and Regression Testing

All

16-Dec-2010

20-Dec-2010

 

(plus)

 

 

 

 

 

 

 

 

 

 

Test Release Candidate

 

21-Dec-2010

21-Dec-2010

 

(plus)

 

 

Release

 

n/a

21-Dec-2010

 

 

 

 

Test Report

 

22-Dec-2010

24-Dec-2010

 

 

Â