February 2026 — Monthly Goals
February 2026 — Monthly Goals
Objectives
# | Objective | App | Status | Owner |
|---|---|---|---|---|
1 | CI/CD pipeline improvements — automated builds and tests | All | Not Started | — |
2 | Loan Accounts module — UI and data layer | Android Client | Not Started | — |
3 | Savings Accounts module — UI and data layer | Android Client | Not Started | — |
4 | KMP shared networking module | Mifos Mobile | Not Started | — |
5 | Mobile Wallet — review and plan iOS port | Mobile Wallet | Not Started | — |
Key Results
CI/CD runs automated tests on every PR for all 5 repos
Loan account list and detail screens functional on Android Client
Savings account list and detail screens functional on Android Client
Shared networking module compiles for Android and iOS targets
Weekly Sprints
Week | Dates | Focus |
|---|---|---|
Week 1 | Feb 2–8 | Sprint planning, CI/CD setup |
Week 2 | Feb 9–15 | Loan module development |
Week 3 | Feb 16–22 | Savings module development |
Week 4 | Feb 23–28 | Integration testing, review |
Notes
—