Feb Week 4 (Feb 23–28) — Integration Testing & Review

Feb Week 4 (Feb 23–28) — Integration Testing & Review

Feb Week 4 (Feb 23–28) — Integration Testing & Review

Sprint Goal

Integration testing for Loan and Savings modules. End-to-end testing, bug fixes, and February retrospective.

Tasks

#

Task

App

Status

Assignee

#

Task

App

Status

Assignee

1

Integration testing — Loan module end-to-end flows

Android Client

Not Started

2

Integration testing — Savings module end-to-end flows

Android Client

Not Started

3

Bug fixes from Loan and Savings testing

Android Client

Not Started

4

UI/UX review and polish for Loan and Savings screens

Android Client

Not Started

5

CI/CD pipeline validation — ensure all repos have working pipelines

All

Not Started

6

KMP networking module — finalize and document API

Mifos Mobile

Not Started

7

Mobile Wallet iOS port — document findings and plan

Mobile Wallet

Not Started

8

February retrospective and March sprint planning prep

All

Not Started

Carry Over from Week 3

Blockers

Retrospective Notes