Discuss  progress of projects and identify any blockers

Discussion items

Time

Item

Who

Notes

Time

Item

Who

Notes

45 min

Check-ins

Everyone



Introductions

Check-Ins

For each student please create a new Level 2 entry and enter the following. 

  • What did you accomplish this past week?

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Rahul Gill

  • What did you accomplish this past week?

    • for mifos-mobile and mobile-wallet apps, all styles are now ui library styles

    • removed default platform styles used in some places in both apps

    • Added screenshots and recordings to the pull requests

  • What will you do this upcoming week?

    • Start using the ui library with android-client app

    • Imrpove lint rules to account some attributes values which are required but are not from ui library

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

    • would like to get these PRs reviewed: uilib#3, mobile-wallet#1333, mifos-mobile#864(since change are dependent on previous ones, so PRs are spliited into multiple commits)

    • Action: Ed to follow up with Chinmay and Devansh to meet regularly 

    • Ed to continue escalating for PR reviews.

Prashant Singh

  • What did you accomplish this past week?

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Hemant Gupta

  • What did you accomplish this past week?

    • PR #2455, #2452 and #2451 raised. Out of these, #2451 and #2452 merged already.

    • completed lombok implementation on - adhocquery, batch, commands module.

  • What will you do this upcoming week?

    • will be raising remaining PRs and continue doing implementation of lombok.

  • What obstacles are impeding your progress?

    • encountered an error related to @RequiredArgsConstructor annotation in PR #2455. Active discussion going on with aleks. Hope will be able to resolve that soon.

  • Would you like help from some mentor for this task? 

    • No

Anika Tibrewala

  • What did you accomplish this past week? 

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Harsh Vardhan

  • What did you accomplish this past week?

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Ramveer Singh 

  • What did you accomplish this past week?

    • Completed end to end functionality for GSIM account which include creation overview, activate.

    • Completed e2e functionality for GLIM account which include creation and overview.

    • Fixed the 1278 issue.

  • What will you do this upcoming week?

    • Looking to start work on unit testing for components or internationalization. Need to discuss with Karan more.

  • What obstacles are impeding your progress?

    • No

  • Would you like help from some mentor for this task?

    • Yes, To start work for next week, need to finalize the library for internationalization and and testing. 

Anmol Gupta

  • What did you accomplish this past week?

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Ziwei Cao

  • What did you accomplish this past week?

    • Studying the Django Restful framework

    • Deploying the current FL function to the Django Restful framework

  • What will you do this upcoming week?

    • Still work on the integration.

    • Anticipate finish this work in the next week

  • What obstacles are impeding your progress?

    • None

  • Would you like help from some mentor for this task? 

    • None

Suchith Donni

  • What did you accomplish this past week?

    • Worked on the django rest API for deploying the model

    • The swagger doc for the version1 API is nearing completion, but still needs lots of improvements

  • What will you do this upcoming week?

    • Continue working on the API and try to get the model deployed.

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task?

    • Nothing as of now!

Prashant Singh

  • What did you accomplish this past week?

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Avinash Vijayvargiya

  • What did you accomplish this past week?

    • Updation of android client - issue with DBflow - ORM dependency for creating database on SQLite

      • Danish waiting to merge but doesn't have repo access 

  • What will you do this upcoming week?

    • Move from findbugs, move to spotbugs, - need to upgrade gradle did successfully to 5.1, then latest version of gradl so all dependencies can be converetd to new version

    • Rahul also did this migration from findbugs to spotbugs  - mobile wallet and mobile banking - had done this for both those apps. 

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

  • Action: Ed to give Danish access to merge pull requests on repository