September 1 Weekly Check-In

September 1 Weekly Check-In

Date

Sep 1, 2020

Attendees

  • @Ed Cable

Discuss  progress of projects and identify any blockers

Discussion items 

Time

Item

Who

Notes

Time

Item

Who

Notes

40 min

Check-ins

Everyone

 

Introductions

Check-Ins

For each student please create a new Level 2 entry and enter the following. 

  • What did you accomplish this past week?

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Ankur Sharma

  • What did you accomplish this past week?

    • Use-case update: Added support for paging while fetching transactions.

    • Created project wiki explaining: project architecture, OBP Backend, Use-cases implemented, project setup, commit guidelines.

    • Documented all my work including research and coding done in the last 3 months: https://gist.github.com/ankurs287/4ef7c3de462073bf36bd5247479cb176

  • What will you do this upcoming week?

    • Wait for the meeting with Istvan to discuss further use-cases and integration with Ace Fintech.

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

  • Showcase: Sept 10

Karan Takalkar

  • What did you accomplish this past week?

    • Documented all pending work, updated main task list, opened Jira tickets as well as web app tickets

    • Updated Project Wiki for df/locale and permissions settings

    • completed FWP

    • some PR reviews, all PRs are merged/closed or reviewed.

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Muskan Khedia

  • What did you accomplish this past week?

    • Completing community app PR on bower dependencies

    • Refactoring modules on web app project

  • What will you do this upcoming week? 

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

Yash Khare

  • What did you accomplish this past week?

    • Gist for final work report

    • Fixed remaining issues. 

  • What obstacles are impeding your progress?

    • Need to know API for submit survey endpoints

  • Would you like help from some mentor for this task? 

  • Action: review Gist and escalate to Nayan for feedback

  • Showcase: Sept 8

Ahmad Jawid Muhammadi

  • What did you accomplish this past week?

    • Wrote UI/Integration tests for group functionalities screen  [Pull Request -> Link]

    • Finished documenting the final work in GSoC'20 [Gist File -> Link]

  • What will you do this upcoming week?

    • continue working on the project 

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task?

  • Showcase: Sept 8

Chinmay Kulkarni 

  • What did you accomplish this past week?

    • Making sure updated SDK review - remaining two PRs got merged

    • Can now get released in 1.4

    • Updated gist for final report

  • What will you do this upcoming week?

    • SDK generation in run-time - published as Jar and could be used as Jar for APIs

      • Publish generated SDK to git repository - developer could send PR to address issues and get those merged. 

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

  • Action: Get SDK call scheduled

  • Showcase: Sept 8

Devansh Aggarwal 

  • What did you accomplish this past week?

    • Working on final report and Payment Hub and Fineract CN integration 

  • What will you do this upcoming week?

    • Discuss the plan for coming weeks with my mentors

    • Work on Request to pay notifications if possible.

  • What obstacles are impeding your progress?

    • Need updates on Fineract's FCM notifications

    • Need meeting with mentors to discuss the further work that needs to be done

  • Would you like help from some mentor for this task?

    • Scheduled a meeting for tomorrow

Garvit Agarwal 

  • What did you accomplish this past week?

    • Resolved merge conflicts in some PRs.

    • Made a Final Report of my Project.(Link)

  • What will you do this upcoming week?

    • Ask my mentor to merge the PRs.

  • What obstacles are impeding your progress? 

    • Same as previous check-in.

  • Would you like help from some mentor for this task? 

    • Yes, for further instructions on GSoC Project.

  • Showcase: Sept 10

Manthan Surkar

  • What did you accomplish this past week? 

    • Finalized swagger, added links to readme

    • Finalized checkstyles

    • Wrote the final GSoC report

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

  • Showcase: Sept 8 or Sept 10

Shashank Priyadarshi

  • What did you accomplish this past week?

    • Worked on a few more conversion.

    • Updated the readme file.

    •  Made the final GSoC report.

  • What will you do this upcoming week?

    • In the upcoming weeks I will do some more Kotlin conversions. 

  • What obstacles are impeding your progress?

    • Updates regarding FCM

  • Would you like help from some mentor for this task? 

  • Action: Ed to follow up again around FCM for Fineract support

  • Showcase: TBD

Rahul Pawar

  • What did you accomplish this past week?

    • Worked on Generic Credit Bureau request-response architecture - commit

    • Fixed the broken Credit Bureau configuration module - commit

  • What will you do this upcoming week? 

    • Complete with the Generic Credit Bureau Architecture.

    • Integration tests and documentation. 

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

  • Showcase: Sept 15 or Sept 17

Shivangi Singh

  • What did you accomplish this past week?

    • Wrote the final work report.

    • Had a further discussion for next steps on the project.

    • Updated the payment hub PR.

  • What will you do this upcoming week?

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task? 

  • Action: Ed to check in with Prashant again. 

  • Showcase: Sept 10. 

Ashwin Ramakrishnan

  • What did you accomplish this past week?

    • Worked on the travis issue with UI tests

    • Had a call with Saksham and decided on change in approach for branch policy and UI testing

    • Notified the devs about the branch policy change

  • What will you do this upcoming week?

    • Write a UI testing template that works well for our case

  • What obstacles are impeding your progress?

    • None

  • Would you like help from some mentor for this task? 

    • No

  • Showcase: Sept 15

Abhijeet Khangarot

  • What did you accomplish this past week?

    • Completed implementation of customer details and other customer sections.

    • Resolved bugs in customer section.

    • Created a roadmap / issues and a project board for future contributors.

    • Worked on dashboard module.

  • What will you do this upcoming week?

    • Work on dashboard module.

    • Work on Savings account page in customers.

  • What obstacles are impeding your progress?

    • None

  • Would you like help from some mentor for this task?

  • Showcase: Sept 10

Yemdjih Kaze Nasser

  • What did you accomplish this past week?

    • Worked on final Gist reports

    • Addressing comments on list and awaiting review PR

  • What will you do this upcoming week?

    • Help work on integration tests to ensure the migration is reliable. 

  • What obstacles are impeding your progress?

  • Would you like help from some mentor for this task?

  • Showcase: Sept 10 

Ashutosh Sharma

  • What did you accomplish this past week?

    • Reviewed some PRs in community app. After that I was not able to work because of internship interviews.

  • What will you do this upcoming week?

    • Will work on community app once internship season gets over.

  • What obstacles are impeding your progress?

    • -

  • Would you like help from some mentor for this task?

  • -Showcase: Sept 15 or 17

Mehul Arora

  • What did you accomplish this past week?

    • Worked on improving the Machine Learning Models

    • Completed gist and got it reviewed

  • What will you do this upcoming week?

    • Prepare for the demo

  • What obstacles are impeding your progress?

    • None

  • Would you like help from some mentor for this task?

    • Not now, but will keep in touch with my mentor

  • Showcase: any day would work.

Subham Pramanik

  • What did you accomplish this past week?

    • Completed gist for GSoC

    • Got GSMA PR approved and merged

    • Clean the codebase and moved code to connector-common and connector-channel

  • What will you do this upcoming week?

    • Prepare for demo and make changes if required

    • Future: receiving side - partially complete 

  • What obstacles are impeding your progress?

    • Nope

  • Would you like help from some mentor for this task? 

    • Nope

  • Action Items:

  • Showcase: TBD

Manish Kumar

  • What did you accomplish this past week? 

  • What will you do this upcoming week?

    • Sign up endpoints

    • Travis failure 

  • What obstacles are impeding your progress?

    • Travis failure

  • Would you like help from some mentor for this task?

    • Action: Ed to provide token so can get travis build running 

  • Showcase: Sept 15 or Sept 17

Percy Ashu

  • What did you accomplish this past week?

    • Gist for final report

  • What will you do this upcoming week?

    • Replacing API in Fineract. 

  • What obstacles are impeding your progress?

    • Test coverage now fails with duplicate classes path.

  • Would you like help from some mentor for this task?

  • Showcase: any day would work . 

Action items